China Tire Manufacturer are Investing In Heavy Equipment & Giant Construction Machinery Tires

China Guizhou Tire Co., Ltd., an all-steel meridian Giant Construction Machinery Tires intelligent manufacturing project, disclosed its environmental impact report.

Hay has learned that the total investment for this project is 292 million yuan, and the planned construction scale is an annual output of 4,968 all-steel meridian Giant Construction Machinery Tires.

Guizhou Tire plans to replace some of its backward production capacity and increase the production capacity of all-steel Giant Construction Machinery radial tires.

Guizhou tire, construction machinery, project filing

They will use the existing special tire workshop building, public works and auxiliary facilities in the second phase of the new plant, remove some old equipment in the original special tire workshop, add necessary new equipment, and modify the corresponding civil construction and pipelines.

It is reported that on July 23, 2019, this project was registered by the Xiuwen County Industrial and Information Bureau of Guiyang City.

Guizhou Tire is a well-known domestic Giant Construction Machinery Tire manufacturer.

In 2015, this company initiated the relocation of the old factory area, and most of the relocations have now ended.

The Guizhou tire new plant is divided into three phases: the first phase of the all-steel engineering radial tire off-site technical transformation project, with an annual output of 260,000 all-steel radial tires, completed and accepted in March 2017; the second phase of the special tire relocation project, with an annual output 3.25 million special tires were completed and accepted in March 2018; the third-phase all-steel radial tire relocation project, with an annual output of 4.9 million all-steel radial tires.

At present, the environmental protection acceptance of the 1.9 million capacity projects in the third phase is completed in 2019, and the remaining 3 million capacity projects are under construction.